Every project is different, but there are typical ranges. These are the timelines we usually see on our own projects.
Typical timelines
- Bathroom remodel: about 1 to 1.5 months.
- Kitchen remodel: about 1 to 1.5 months.
- Home addition: usually 10 to 12 months.
- ADU: usually 10 to 12 months.
Why additions and ADUs take longer
A kitchen or bathroom remodel that keeps its walls can often be permitted without plan check. An addition or an ADU is new construction. It needs plans, engineering and plan check before the permit is issued, and then a foundation, framing, roofing and every trade that follows. Each stage is inspected.
What affects the schedule
- Permits. The type of permit and the agency reviewing it set the pace at the start of the project.
- Selections. Cabinets, stone, tile and appliances have to be chosen and ordered. Decisions made late hold up the work.
- What is inside the walls. In older homes, you do not know what is behind the walls until they are opened. Repairs are made before the walls are closed.
- Changes during the job. A change after work has started usually adds time.
How to keep a project on schedule
- Settle the scope in writing before work begins.
- Make your selections early, so materials are on hand when they are needed.
- Stay available for decisions. Questions come up, and quick answers keep the job moving.
We take on a limited number of projects at a time and stay on each job from start to finish.
To talk about your project and its schedule, contact us or request an appointment.
Related reading
- Do You Need a Permit to Remodel a Kitchen or Bathroom in Los Angeles?
- What We Find Inside the Walls of Older Los Angeles Homes
- What to Expect During a Custom Build, Phase by Phase
Questions
How long does a bathroom remodel take?
On Jencor projects, a bathroom remodel typically takes about 1 to 1.5 months.
How long does a kitchen remodel take?
On Jencor projects, a kitchen remodel typically takes about 1 to 1.5 months.
How long does it take to build an ADU or a home addition?
Usually 10 to 12 months. Additions and ADUs need plans, plan check and a full sequence of construction and inspections.
Planning a project in Los Angeles? Send Corey a note or call (310) 770-7707. Rules and requirements depend on the specific property; confirm with the city or county before you build.