Altadena is an unincorporated community, so a rebuild there is permitted by Los Angeles County, not by the City of Pasadena or the City of Los Angeles. The County has set up a dedicated process for Eaton Fire properties. This article explains how that process works and what a general contractor handles along the way.
Who issues the permit
A County rebuild is reviewed by several departments: Regional Planning for zoning, Public Works Building and Safety for the building permit, the Fire Department, and Public Health where a septic system is involved.
The County runs a One-Stop Permit Center for Eaton Fire rebuilds at 464 W. Woodbury Road, Suite 210, in Altadena. It is open Monday through Friday, and rebuild consultations can be booked by appointment. The County's published target is 10 business days for each department's first review and 5 business days for rechecks.
Like-for-like or a new design
The first decision is whether the new house will be a like-for-like rebuild.
- Like-for-like. The County defines this as a structure of the same size, in the same location and for the same use as the one that was lost. The floor plan can change, and the house can be smaller. In the Eaton Fire area, the County allows an increase in floor area, height or footprint of up to 10 percent or 200 square feet, whichever is greater.
- Not like-for-like. A larger or relocated house must meet current zoning, including the Altadena Community Standards District.
A like-for-like rebuild does not have to meet the current Zoning Code, which makes planning review faster. It still has to meet the current Building, Fire, and Health and Safety codes.
Before a permit can be issued
Debris removal has to be finished first. The County requires both phases, hazardous material removal and fire debris removal, to be complete before a building permit is issued.
What the new house has to meet
Because the house is new construction, it is built to today's codes. According to the County, that includes fire sprinklers, and in mapped fire hazard zones it includes the state's wildfire construction standards for roofing, vents, siding and windows. Homes must be solar-ready and electric-ready.
If the property is on a septic system, Public Health reviews it. An existing system in good working order can generally be kept when the rebuild has the same number of bedrooms.
Fees and deadlines
- Fee waivers. In June 2025, the Board of Supervisors approved waiving and refunding certain County permit fees for owners who owned and lived in their home before January 7, 2025.
- Application deadline. The County's rebuilding guidance says like-for-like applications should be filed within two years of the emergency declaration, with extensions possible. That two-year mark arrives in January 2027, so confirm your date with Regional Planning.
- Permit life. A building permit expires if construction does not begin within 12 months.
Living on the property during the rebuild
The County allows temporary housing, such as an RV or manufactured home, on a fire-damaged lot with the proper utility connections. Under state law, a detached ADU can also be finished and occupied before the main house.
What a general contractor handles
- Site walk and budget. We look at the lot, foundation, retaining walls, utilities and access, and give you a budget range based on your property.
- Insurance estimate. We provide the detailed, line-by-line estimate your adjuster needs. We do not negotiate your claim.
- Design and permits. We work with your architect or a County pre-approved plan, coordinate engineering and energy reports, and manage plan check corrections with each department.
- Construction. One team runs the job from foundation through final inspection.
- Final inspections. We schedule inspections and see the house through to its certificate of occupancy.
Jencor is a licensed general contractor (#968170) and takes on fire rebuilds. See our fire rebuild service or contact us to walk your lot.
Sources
- Los Angeles County Recovers: Like-for-Like Rebuild
- Los Angeles County Recovers: Frequently Asked Questions
- Los Angeles County Recovers: One-Stop Permit Centers
Related reading
- Rebuilding After the LA Fires: Where Things Stand
- Zone 0 Wildfire Rules
- How to Verify a Licensed General Contractor in California
Questions
Who issues building permits for an Altadena fire rebuild?
Los Angeles County. Altadena is unincorporated, so rebuilds are reviewed by County Regional Planning, Public Works Building and Safety, the Fire Department and, where septic is involved, Public Health.
What counts as a like-for-like rebuild in Altadena?
A structure of the same size, in the same location and for the same use as the one that was lost. In the Eaton Fire area, the County allows an increase of up to 10 percent or 200 square feet, whichever is greater.
Can I get a permit before debris removal is finished?
No. The County requires hazardous material removal and fire debris removal to be complete before a building permit is issued.
Planning a project in Los Angeles? Send Corey a note or call (310) 770-7707. Rules and requirements depend on the specific property; confirm with the city or county before you build.